Friday, February 3, 2017

SPILLWAY RIP RAP PROJECT UPDATE 2/3/17

Virginia Waters and Wetlands has made excellent progress over the last few weeks on the spillway rip rap project. As of this afternoon the rough grading/shaping has been completed and about 50% of the rip rap has been installed. If all goes as planned, and the weather continues to cooperate, we hope to have all of the stone installed in the couple of weeks.

The images below are sequential starting with the delivery of the first piece of machinery and the last being taken today.











This last picture is a bonus for those of you who hung with me to the end of this pic heavy post. This beautiful breeding pair of Bald Eagles was spotted by the lake this week. Thanks Virginia Waters for sharing this image with us!